 - Engineering Step-by-Step
 - Subsystem Integration
 - Enlighted Energy Manager
 - Enlighted Energy Manager Additional Procedures
 - Modifying Lighting Demand Response Schedules
 
Modifying Lighting Demand Response Schedules
- In System Browser, select Project > Field Networks > [SORIS network] > [Enlighted adapter] > [Enlighted energy manager] > Demand Responses. 
NOTE: You can modify only demand response schedules that have not yet started. 
- In the Extended Operation tab, do the following:
a. In the ID field, enter the identifier of the demand response that you want to modify and click Save. 
b. Modify one or more of the following settings and click Save: 
- Duration
- Price Level
- Pricing 
- Start Time
c. Next to the DR Configuration property, click Update DR. 
 
- The selected demand response schedule is updated.