Scheduling in SICLIMAT X
This section provides instructions for schedules in SICLIMAT X. For related background information, see the reference section.
Prerequisites
- In System Browser, Application View is selected.
 
Add a New SICLIMAT X Schedule
- Select Applications > Schedules > Siclimat Schedules.
 
- Click Add New 
 and select New Siclimat Schedule. 
- Click the Outputs tab, and then drag any objects from System Browser you want associated with the schedule.
 
- From the Setup tab, complete the following: 
a. From the Start Date drop-down list, select the start date for the schedule. Selecting the Any date check box defaults to the current date.
b. From the End Date drop-down list, select the end date for the schedule. Selecting the Any date check box defaults to an infinite date. 
- Click Save 
. 
- Complete the Name and Description fields.
 
- Click OK.
 
Copy a SICLIMAT X Schedule
- Select Applications > Schedules > Siclimat Schedules.
 
- Open the schedule you want to copy.
 
- Click Save As 
. 
- Complete the Name and Description fields.
 
- Click OK.
 
Delete a SICLIMAT X Schedule
- Select Applications > Schedules > Siclimat Schedules.
 
- Open the schedule you want to delete.
 
- Click Delete 
. 
- Click OK.
 
Add a Weekly Schedule Entry
- Select Applications > Schedules > Siclimat Schedules.
 
- Open the schedule to which you want to add a new weekly schedule entry.
 
- Right-click in the schedule area and then select Add New Weekly Schedule Entry.
 
- From the Schedule Entries tab, complete the Time and Value fields.
 
- Click Save 
. 
Modify a Weekly Schedule Entry
- Select Applications > Schedules > Siclimat Schedules.
 
- Open the schedule you want to modify.
 
- In the schedule area, click the weekly schedule you want to modify. Schedules are highlighted with a blue bar on the side of the entry.
 
- In the Schedule Entries tab, modify the Time and Value fields as needed. 
NOTE: You can also drag the blocks up and down in the daily and weekly views to adjust the time. For more information, see SICLIMAT X Schedules. 
- Click Save 
. 
Delete a Weekly Schedule Entry
- Select Applications > Schedules > Siclimat Schedules.
 
- Open the schedule with the weekly schedule entry you want to delete.
 
- Click the weekly schedule that contains the entry you want to delete.
 
- Details display in the Schedule Entries tab.
 
- In the Schedule Entries tab, locate the entry you want to delete and click Delete 
. 
NOTE: You cannot delete default values. 
- Click Save 
. 
Add an Exception Entry
- Select Applications > Schedules > Siclimat Schedules.
 
- Open the schedule to which you want to add an exception entry.
 
- Click the Exceptions tab.
 
- Click New.
 
- Complete the Time and Value fields.
 
- Click Save 
. 
Modify an Exception Entry
- Select Applications > Schedules > Siclimat Schedules.
 
- Open the schedule with the exception entry you want to modify.
 
- Click the Exceptions tab.
 
- From the list, select the exception you want to modify.
 
- Modify the fields as needed.
 
- Click Save 
. 
Delete an Exception Entry
- Select Applications > Schedules > Siclimat Schedules.
 
- Open the schedule with the exception entry you want to delete.
 
- Click the Exceptions tab.
 
- Select the exception entry you want to delete, and then click Delete 
. 
- Click Save 
. 